24/15 = x/18
Solve for x.
It takes 15 electricians 24 days to wire a new housing subdivision. How many days would 18 electricians require to do the same job?
8 answers
x=28.8
28.8/18=1.6
it takes them 20 days
Wow way to show your work
15/18 = .8333333(infinite)
15/18 x 24 = 20
(Yes I was the person complaining about lack of work)
15/18 x 24 = 20
(Yes I was the person complaining about lack of work)
and i was the one who did not show the work
It takes 15 electricians 24 days to wire a new housing subdivision. How many days would 18 electricians take to do the same job, assuming all electricians work at the same pace?