If a job can be done by 10 workers in 5 hours, the work load is 10(5) = 50 man-hours. If 4 workers is doing the job for 6 hours, the work done is 4(6) = 24 man-hours. A remaining of 50 - 24 = 26 man-hours of work still needs to be done.
Problem
Eleven men could finish the job in 15 days. Five men started the job and four men were added at the beginning of the sixth day. How many days will it take them to finish the job?