) FIVE JOBS ARE SCHEDULED IN TWO MACHINES IN A MANUFACTURING SHOP. AL FIVE JOBS ARE TO UNDERGO PROCESSING IN BOTH THE MACHINES SEQUENTIALLY
PROCESSING TIMES IN MINUTES
JOB NO MACHINES1 MACHINE 2
1 4 7
2 6 3
3 2 3
4 7 7
5 8 6
A) IDENTIFY THE BEST SEQUENCE USING JOHNSON’S RULE
B) DEVELOP A GANTT CHART FOR SCHEDULE AND COMPUTE FLOW TIMES