Calculate the total bid we should offer for a project with below info:
Construction material: $30/lb
Material needed: 10000 lb
PM salary: $100/h
PM hours: 200
Office space: $4000/month
Project duration: 6 months
Other overhead costs: 10% of direct costs
Administration costs: $10000
Profit: 20% of total cost