A time study of operations yielded the following observed times for one element of the job; the analyst gave a performance rating of 1.13. Using an allowance of 20%, determine the appropriate standard time for this operation.
Observations Time, x
1 1.12
2 1.15
3 1.16
4 1.12
5 1.15