A project has been defined to contain the following list of activities along with their required times for completion.
Activity No.
Activity
Time (Weeks)
Immediate Predecessors
1
Colect requirements
2
-
2
Analyze processes
3
1
3
Analyze data
3
2
4
Design processes
7
2
5
Design data
6
2
6
Design screens
1
3, 4
7
Design reports
5
4, 5
8
Program
4
6, 7
9
Test and document
8
7
10
Install
2
8, 9
a. Draw a network diagram chart for the activities.
b. Calculate the earliest expected completion time.
c. Show the critical path.
d. What would happen if activity 6 were revised to take six weeks instead of one week?
e. Construct a Gantt chart for the project defined above.