A project demand for electricity is 25,000MW in a year. Estimate the following: The electricity is produced by a big hydroelectric station and the water level in the 10m deep reservoir is allowed to fall 100m to generate the electricity. How many square kilometer must the reservoir cover. Assume 100% efficiency.

1 answer

pls responds to my questions