A process for producing electronic circuits has achieved very high yield levels. An average of only 10 defective parts per million is currently produced.

1. What are the upper and lower control limits for a sample size of 100?

2. Recompute the upper and lower control limits for a sample size of 10,000?

3. Which of these two sample sizes would you recommend? Explain.

Management has reconsidered the method of quality control and has decided to use process control by variables instead of attributes. For variables control a circuit voltage will be measured based on a sample of only five circuits. The past average voltage for samples of size 5 has been 3.1 volts, and the range has been 1.2 volts.

1. What would the upper and lower control limits be for the resulting control charts (average and range)?

2. Five samples of voltage are taken with the results in the table below. What action should be taken if any?

3. Discuss the pros and cons of using this variables control chart versus the control chart discussed in the first part of the assignment. Which do you prefer?

Ex. 1 2 3 4 5
x 3.6 3.3 2.6 3.9 3.4
R 2.0 2.6 0.7 2.1 2.3

1 answer

Answer
Similar Questions
  1. QuestionHow do high levels of net immigration impact the demographics of a developed country?(1 point) High levels of
    1. answers icon 1 answer
    1. answers icon 1 answer
    1. answers icon 1 answer
    1. answers icon 3 answers
more similar questions