A planner estimates that a project will take 3.0 years to complete. Write the corresponding number of days with the appropriate number of significant figures (one year is 365.25 days long).

1 answer

LOL
You only have two significant figures in 3.0

365.25 * 3.0 = 1095.75
which to two sig figs is
11*10^2