A factory that runs 24 hours a day, 7 days a week, has shifts for its workers that are 7 hours long. If a shift starts on Sunday morning at 6AM, at what time does the earliest shift on the next Friday start?

3 answers

Determine total hours between Sunday morning at 6AM to 12AM midnight Friday = 114hrs.
In the 114hr, 16 full shifts would have would have been completed --ie 114hrs/7hrs = 16.
Total time for 16 shifts is 16 * 7 =112hrs.
So that means a new shift started at 10PM on Thursday and will run until 5AM Friday.
Therefore the earliest shift on the next Friday start at 5AM