The volume of one tub is 3 yards long x 2 yards wide x 1 yard high = 6 cubic yards.
The total volume of all 325 tubs is 325 tubs x 6 cubic yards per tub = 1950 cubic yards.
Therefore, the factory will need 1950 cubic yards - 1800 cubic yards = 150 cubic yards more concrete than the manager's estimate to completely fill all of the tubs.
A factory is filling 325 rectangular-prism tubs, like the one shown, with concrete. The manager estimates that the factory will need 1800 cubic yards of concrete to completely fill all of the tubs.
A tub in the shape of a rectangular prism. It is 3 yards long, 2 yards wide, and 1 yard high.
Question
How much ,begin emphasis,more,end emphasis, concrete than the manager's estimate will the factory need to completely fill all of the tubs? Enter the answer in the box.
1 answer