                if 8 men can do a job in days, what is the percentage increase in number of days required to do the job when 2 men are released?
not just an answer please.
A.16 2/3%
B.25%
C. 33 1/3%
D.40%
E.48%
            
        not just an answer please.
A.16 2/3%
B.25%
C. 33 1/3%
D.40%
E.48%
Answers
                    Answered by
            Steve
            
    6 men is 3/4 of 8 men
So, they can only do 3/4 as much work in a day.
So, it takes 4/3 as many days, or
(C)
    
So, they can only do 3/4 as much work in a day.
So, it takes 4/3 as many days, or
(C)
                    Answered by
            Reiny
            
    suppose it took n days
number of man-days = 8n
if done by 6 men
number of days = 8n/6 = 4n/3
change in days = 4n/3 - n = (1/3)n
percentage change = (1/3)n / n = 1/3 or 33 1/3%
    
number of man-days = 8n
if done by 6 men
number of days = 8n/6 = 4n/3
change in days = 4n/3 - n = (1/3)n
percentage change = (1/3)n / n = 1/3 or 33 1/3%
                                                    There are no AI answers yet. The ability to request AI answers is coming soon!
                                            
                Submit Your Answer
We prioritize human answers over AI answers.
If you are human, and you can answer this question, please submit your answer.