Asked by major
                10. A house painter can finish a house in 6 hours. His partner can finish the same house in 12 hours. Which of the
following is the number of hours it would have taken them to finish painting the house if they had worked together?
A. 3 hours
B. 4 hours
C. 6 hours
D. 9 hours
            
        following is the number of hours it would have taken them to finish painting the house if they had worked together?
A. 3 hours
B. 4 hours
C. 6 hours
D. 9 hours
Answers
                    Answered by
            Steve
            
    1/x = 1/6 + 1/12
x = 4
    
x = 4
                                                    There are no AI answers yet. The ability to request AI answers is coming soon!
                                            
                Submit Your Answer
We prioritize human answers over AI answers.
If you are human, and you can answer this question, please submit your answer.