Sixty men working on a construction job have done 1/3 of the work in 18 days. The project is behind schedule and must be accomplished in the next twelve days. How many more workers need to be hired?

Answers

Answered by MathMate
Each person accomplishes 1/3÷(60*18) of the project, 1/3240 per person per day.
To finish 2/3 of the project in 12 days,
Total number of workers need
=2/3 ÷ (12*(1/54)
=(2/3)*(3240/12)
=180
Therefore 120 more workers are needed.
Answered by Shin
120 or 180? :)
Answered by MathMate
Therefore 120 <i>more</i> workers are needed.
Answered by Shin
Thanks :)
Answered by MathMate
You're welcome!
Answered by jaymar
where did you get 54? ty