Sixty men working on a construction job have done 1/3 of the work in 18 days. The project is behind schedule and must be accomplished in the next twelve days. How many more workers need to be hired?
Answers
Answered by
MathMate
Each person accomplishes 1/3÷(60*18) of the project, 1/3240 per person per day.
To finish 2/3 of the project in 12 days,
Total number of workers need
=2/3 ÷ (12*(1/54)
=(2/3)*(3240/12)
=180
Therefore 120 more workers are needed.
To finish 2/3 of the project in 12 days,
Total number of workers need
=2/3 ÷ (12*(1/54)
=(2/3)*(3240/12)
=180
Therefore 120 more workers are needed.
Answered by
Shin
120 or 180? :)
Answered by
MathMate
Therefore 120 <i>more</i> workers are needed.
Answered by
Shin
Thanks :)
Answered by
MathMate
You're welcome!
Answered by
jaymar
where did you get 54? ty
There are no AI answers yet. The ability to request AI answers is coming soon!
Submit Your Answer
We prioritize human answers over AI answers.
If you are human, and you can answer this question, please submit your answer.