                Three men are working together can finish a house repair job in 10 days. How many days will 5 men working at the same rate finish the same job?
            
            
        Answers
                    Answered by
            Reiny
            
    number of "mandays" needed = 3(10) = 30
number of days with 5 men = 30/5 = 6 days
    
number of days with 5 men = 30/5 = 6 days