Ask a New Question

Asked by Mayank

3 men and 4 boys can do a piece of work in14 days , while 4 men and 6 boys do the same work in 10 days . How long would it take one man to finish the same work?
13 years ago

Answers

Answered by Steve
1/14 = 3/m + 4/b
1/10 = 4/m + 6/b

m = 70
b = 140
13 years ago
There are no AI answers yet. The ability to request AI answers is coming soon!

Submit Your Answer


We prioritize human answers over AI answers.

If you are human, and you can answer this question, please submit your answer.

Related Questions

2 men and 5 boys can do a piece of work in 4 days, while 4 men and 4 boys can do it in 3 days.How lo... A boy boys 9 Apple a boy boys 9 Appl a boy buys 9 Apple 4 rupees 9.60 and sells them at 11 for rupe... A piece of metal A and a piece of metal B of the same mass and at the same temperature of 80°C are d... A character piece is a piece of solo piano music from the Romantic period that conveys a particular... 1. Where is the little boys' room? 2. Where is the little girls' room? [Is the person looking for... !!BOYS ONLY!! this is not school related I want a bf im 12 I have long brown hair hazel ey... 1. Why do many boys like to read stories about Davy Crockett? 2. Who were some of the famous peo... Why boys should help in the kitchen Need Boys #'s there are twice as many boys in classas there are girls.are there more girls or boys in class? the...
Submit Your Answer

Question

3 men and 4 boys can do a piece of work in14 days , while 4 men and 6 boys do the same work in 10 days . How long would it take one man to finish the same work?

Ask a New Question
Archives Contact Us Privacy Policy Terms of Use