You currently lease scanning equipment at a cost of $1,500 per quarter and two copy machines at $120 per month. What will you need to budget annually for this leased equipment
Answers
Answered by
Bosnian
4 * 1,500 + 2 * 120 * 12 = 6,000 + 2,880 = 8,880 $
Answered by
lisa
A coding supervisor must determine the number of FTEs needed to code 500 discharges per week. If it takes an average of 20 minutes to code each record and each record and each coder works 32 productive hours per week,how many FTEs will the coding supervisor need?
Answered by
Anonymous
500/32=15.6