Asked by Gracie

1. The time required to complete a project is normally distributed with a mean of 80 weeks and a standard deviation of 10 weeks. The construction company must pay a penalty if the project is not finished by the dues date of the contract. If a construction company bidding on this contract wishes to be 90 percent sure of finishing by the due date, what due date (project week #) should be negotiated?

Answers

Answered by MathGuru
Use z-scores.

Formula:
z = (x - mean)/sd

You are looking to solve for x, so fill in the rest of the formula with what you know.

Find z using z-table (problem gives you percentage). Mean = 80 and standard deviation = 10.

I hope this will help get you started.
Answered by Anonymous
88.1594
Answered by Lebohang
the time requested to complete a project is normally distributed with a mean of 80 weeks and standard deviation of 10 weeks. the construction company must pay a penalty if the project is not finished by the due date in the contract. If a construction company bidding on this contract wishes to be 90 percent sure if finishing by the due date, what due date (project week number) should be negotiated?
Answered by Anonymous
92.8