Asked by taylor
bernie began building a model airlane on day 7 of his summer vacation and finished building it on day 65. he worked on the plane each day. how many days did it take?
Answers
Answered by
taylor
Please help me i really need help before school help me
Answered by
Reiny
Taylor, you are probably just taking 65-7 and get 58
, but that would not count day 7,
So there are 59 days.
Looks at a simpler case:
How many days from June 1 to june 5
obviously there are 5 days, but ...
when I take 5-1 I get only 4.
so that is why I had to add 1 to the subtraction answer.
, but that would not count day 7,
So there are 59 days.
Looks at a simpler case:
How many days from June 1 to june 5
obviously there are 5 days, but ...
when I take 5-1 I get only 4.
so that is why I had to add 1 to the subtraction answer.
There are no AI answers yet. The ability to request AI answers is coming soon!
Submit Your Answer
We prioritize human answers over AI answers.
If you are human, and you can answer this question, please submit your answer.