Asked by Ramesh Reddy
Please guide me to solve the below problem:
'A'an do 2/3 of a work in 40 days.'B'can do 1/2 of the work in 75 days.'C'can do 3/4of work in 75 days.If all them together work in how many days will they do 5/6 0f the work.
I had solved the above problem like this:
A can do the work=3/2*40=60 days.
A's one day work =1/60
B can do the work=2/1*75=150 days
B's one day work=1/150
C can do the work=4/3*75=100 days.
C's one day the work=1/100
They together=1/60+1/150+1/100
=5+2+3/100
=10/300=1/30
They complete the 5/6 of the work =1/30*5/6
=1/36
Therefore ,they complete the 5/6 of the work in 36 days.
'A'an do 2/3 of a work in 40 days.'B'can do 1/2 of the work in 75 days.'C'can do 3/4of work in 75 days.If all them together work in how many days will they do 5/6 0f the work.
I had solved the above problem like this:
A can do the work=3/2*40=60 days.
A's one day work =1/60
B can do the work=2/1*75=150 days
B's one day work=1/150
C can do the work=4/3*75=100 days.
C's one day the work=1/100
They together=1/60+1/150+1/100
=5+2+3/100
=10/300=1/30
They complete the 5/6 of the work =1/30*5/6
=1/36
Therefore ,they complete the 5/6 of the work in 36 days.
Answers
Answered by
bobpursley
Here is another way:
rate=rate1+rate2+rate3
= W/60+W/150+W/100= W(5+2+3)/300
= W/30 check same as yours.
So time= amountwork/rate= 5W/6 /(W/30)
time= 150/6=25 days
So our answers are different, check mine, then yours.I don't agree with how you get 1/36, time= work/rate, not multiplied
rate=rate1+rate2+rate3
= W/60+W/150+W/100= W(5+2+3)/300
= W/30 check same as yours.
So time= amountwork/rate= 5W/6 /(W/30)
time= 150/6=25 days
So our answers are different, check mine, then yours.I don't agree with how you get 1/36, time= work/rate, not multiplied
There are no AI answers yet. The ability to request AI answers is coming soon!
Submit Your Answer
We prioritize human answers over AI answers.
If you are human, and you can answer this question, please submit your answer.