1st crew did (1/6)job
that leaves (5/6)job to be done with combined crews.
combined rate = job/6 + job/4 = 5job/12
time to do rest of job = (5/6)job รท (5job/12)
= 2 hours
It will take another 2 hours to finish
that leaves (5/6)job to be done with combined crews.
combined rate = job/6 + job/4 = 5job/12
time to do rest of job = (5/6)job รท (5job/12)
= 2 hours
It will take another 2 hours to finish