A company makes three products X, Y and Z. Each product requires processing by three machines A, B and C. The time required to...Asked by kIM
A company makes three products X, Y and Z. Each product requires processing by three machines A, B and C. The time required to produce one unit of each product is shown below.
Product X:-
Machine A: 1
Machine B: 2
Machine C: 2
Product Y:
Machine A:2
Machine B: 2
Machine C: 2
Product Z:
Machine A:2
Machine B: 1
Machine C:4
The machines are available for 200, 525 and 350 hours each month. How many units of each product can be manufactured per month if all three machines are utilized to their full capacity?
Product X:-
Machine A: 1
Machine B: 2
Machine C: 2
Product Y:
Machine A:2
Machine B: 2
Machine C: 2
Product Z:
Machine A:2
Machine B: 1
Machine C:4
The machines are available for 200, 525 and 350 hours each month. How many units of each product can be manufactured per month if all three machines are utilized to their full capacity?
Answers
Answered by
Qwabena Jerry
Please what will be the draws for tomorrow Friday bonanza 13 august 21
There are no AI answers yet. The ability to request AI answers is coming soon!
Submit Your Answer
We prioritize human answers over AI answers.
If you are human, and you can answer this question, please submit your answer.