The correct order of the controlling process is:
A Establish standards → Measure Actual performance → Evaluate performance → Take corrective action
So the answer is A.
A Establish standards =Measure Actual performance= Evaluate performance = Take corrective action
B Take corrective action= Establish standards= Evaluate performance= Measure Actual performance
C Measure Actual performance= Establish standards= Take corrective action= Evaluate performance
D Evaluate performance = Take corrective action= Establish standards = Measure Actual performance
1 answer
The correct order of the controlling process is:
A Establish standards → Measure Actual performance → Evaluate performance → Take corrective action
So the answer is A.