Question
The following direct materials and direct labor data pertain to the operations of Solario Manufacturing Company for the month of August
Costs
Quantities
Actual labor rate $13 per hour Actual hours incurred and used 4,200 hours
Actual materials price $128 per ton Actual quantity of materials purchases and used 1,225 tons
Standard labor rate $12 per hour Standard hours used 4,300 hours
Standard materials price $130 per ton Standard quantity of materials used 1,200 tons
Compute the total, price, and quantity variances for materials and labor.
Total materials variance $ UnfavorableFavorable
Materials price variance $ FavorableUnfavorable
Materials quantity variance $ UnfavorableFavorable
Total labor variance $ FavorableUnfavorable
Labor price variance $ UnfavorableFavorable
Labor quantity variance $ UnfavorableFavorable
Costs
Quantities
Actual labor rate $13 per hour Actual hours incurred and used 4,200 hours
Actual materials price $128 per ton Actual quantity of materials purchases and used 1,225 tons
Standard labor rate $12 per hour Standard hours used 4,300 hours
Standard materials price $130 per ton Standard quantity of materials used 1,200 tons
Compute the total, price, and quantity variances for materials and labor.
Total materials variance $ UnfavorableFavorable
Materials price variance $ FavorableUnfavorable
Materials quantity variance $ UnfavorableFavorable
Total labor variance $ FavorableUnfavorable
Labor price variance $ UnfavorableFavorable
Labor quantity variance $ UnfavorableFavorable
Answers
Related Questions
E11-6 The following direct materials and direct labor data pertain to the operations of
Batista Man...
P20-2A
For the year ended December 31, 2010, the job cost sheets of DeVoe Company conta...
The East Company manufactures several different products. Unit costs associated with Product ORD203...
The Thompson Company uses standard costing and has established the following direct material and dir...