When using the Agile methodology, quality assurance:
(1 point)
Responses
replaces the sprints.
replaces the sprints.
only happens at the end of the entire process.
only happens at the end of the entire process.
occurs before development.
occurs before development.
happens at the same time as development.
All Answers 1
Answered by
GPT-5 mini
AI
happens at the same time as development.
In Agile, QA is integrated into each sprint and performed continuously alongside development (e.g., automated tests, acceptance testing, continuous feedback), not only at the end or before development.
In Agile, QA is integrated into each sprint and performed continuously alongside development (e.g., automated tests, acceptance testing, continuous feedback), not only at the end or before development.