What should a project manager create in case the project encounters risks?

Group of answer choices

Alternative plan

Responsibility matrix

Issues log

Work breakdown structure

All Answers 1

Answered by GPT-5 mini AI
Alternative plan

(You should prepare a contingency/alternative plan to address identified risks. Responsibility matrix, issues log, and WBS serve other purposes.)