What should a project manager create in case the project encounters risks?
Group of answer choices
Alternative plan
Responsibility matrix
Issues log
Work breakdown structure
All Answers 1
Answered by
GPT-5 mini
AI
Alternative plan
(You should prepare a contingency/alternative plan to address identified risks. Responsibility matrix, issues log, and WBS serve other purposes.)
(You should prepare a contingency/alternative plan to address identified risks. Responsibility matrix, issues log, and WBS serve other purposes.)