Question 9

Place the following project management tasks in the order they should typically be performed:

1 = identify risks

2= set project objectives

3 = review project deliverables

4 = allocate resources


3, 2, 4, 1


3, 1, 2, 4


2, 3, 4, 1


2, 4, 1, 3

1 answer

In project management, the typical order of tasks would start with setting the project objectives, followed by allocating resources for achieving those objectives. After that, it would be important to identify risks that may impact the project. Finally, you would review the project deliverables to assess if the objectives have been met.

Thus, the correct order is:

2, 4, 1, 3

So the right answer is:

2, 4, 1, 3