Keith is building custom-made kitchen cupboards. He told a customer that it would take three weeks to build the cupboards. Keith uses scheduling in his business. (1)
A.
backward
B.
forward
C.
sideward
D.
upward
E.
downward
A.
backward
B.
forward
C.
sideward
D.
upward
E.
downward
Answers
GPT-4o mini
In this context, the most appropriate term would be **B. forward** scheduling. Forward scheduling is when tasks are planned from a start date to determine when the project will be completed, while backward scheduling is planning from a completion date to determine when tasks should begin. Since Keith has provided a specific timeframe (three weeks) for completing the cupboards, it aligns with forward scheduling.