A computer manufacturer assembled 21,000 computers in October. For the month of November, they expect to double production. If a worker can assemble one computer per day, how many workers will be needed to complete the job in 28 days?

a. 1,500 workers
b. 750 workers
c. 1,429 workers
d. 4,500 workers

Answers

Answered by Ms. Sue
21,000 / 28 = ?

Answered by Jen
I think you would then multiply that by 2, since it says to expect double production..?
Answered by Ms. Sue
Oops! You're right, Jen. :-)

42,000 / 28 = ?

Answered by Ross
1,500 workers