A solar energy project is expected to have capital costs of $995,000, average yearly operating costs of $175,000, and a lifetime of 25 years. If the total production during the lifetime of the project is 89,500,000 kWh, what is the levelized cost of energy (LCOE)?(1 point)

Responses

$0.06 per kWh
$0.06 per kWh

$0.60 per kWh
$0.60 per kWh

$0.07 per kWh
$0.07 per kWh

$0.77 per kWh

1 answer

To calculate the levelized cost of energy (LCOE), we can use the formula:

\[ LCOE = \frac{Total\ Lifetime\ Costs}{Total\ Lifetime\ Energy\ Production} \]

Step 1: Calculate Total Lifetime Costs.

Total Lifetime Costs consist of two components:

  1. Initial Capital Costs: $995,000
  2. Total Operating Costs over 25 years:

\[ Total\ Operating\ Costs = Average\ Yearly\ Operating\ Costs \times Lifetime \]

\[ Total\ Operating\ Costs = 175,000 \times 25 = 4,375,000 \]

Adding both components:

\[ Total\ Lifetime\ Costs = Capital\ Costs + Total\ Operating\ Costs \]

\[ Total\ Lifetime\ Costs = 995,000 + 4,375,000 = 5,370,000 \]

Step 2: Calculate Total Lifetime Energy Production.

The total energy production during the lifetime provided is 89,500,000 kWh.

Step 3: Calculate LCOE.

Now we can substitute the values into the LCOE formula:

\[ LCOE = \frac{5,370,000}{89,500,000} \]

Calculating this gives:

\[ LCOE \approx \frac{5,370,000}{89,500,000} \approx 0.05997 \]

Rounding this to two decimal places gives us:

\[ LCOE \approx 0.06 \]

Thus, the levelized cost of energy is approximately $0.06 per kWh.

So the correct response is:

$0.06 per kWh