Question

a project involves degree of uncertainty that remains the same as the project progresses.
true or false

Answers

GPT-4o mini
False. In most projects, the degree of uncertainty typically decreases as the project progresses. Initially, there is often greater uncertainty regarding scope, time, and costs. As the project moves forward, more information becomes available, and risks can be managed or mitigated, which helps to reduce uncertainty. However, it's also possible for new uncertainties to arise during the project, particularly if changes occur or unforeseen challenges arise. Overall, while some uncertainties may remain constant, the general trend is that uncertainty decreases over time.