To calculate the NPV (Net Present Value) of the project, we'll follow these steps:
-
Calculate Initial Investment:
- Cost of the machine = $10.55 million
- Transport and installation cost = $58,505.00
- Total Initial Investment = Cost of the machine + Transport and installation cost \[ \text{Total Initial Investment} = 10,550,000 + 58,505 = 10,608,505 \]
-
Calculate Annual Depreciation:
- Depreciable life = 5 years
- Salvage value = $0
- Annual Depreciation = Initial Investment / Depreciable Life \[ \text{Annual Depreciation} = \frac{10,608,505}{5} = 2,121,701 \]
-
Calculate Annual Operating Cash Flow:
- Incremental Revenues = $4.26 million = $4,260,000
- Incremental Costs = $1.40 million = $1,400,000
- Operating Income (EBIT) = Incremental Revenues - Incremental Costs - Depreciation \[ \text{Operating Income (EBIT)} = 4,260,000 - 1,400,000 - 2,121,701 = 738,299 \]
- Tax (38%) = EBIT * Tax Rate \[ \text{Tax} = 738,299 \times 0.38 = 280,561.62 \]
- Net Income = EBIT - Tax \[ \text{Net Income} = 738,299 - 280,561.62 = 457,737.38 \]
- Operating Cash Flow = Net Income + Depreciation \[ \text{Operating Cash Flow} = 457,737.38 + 2,121,701 = 2,579,438.38 \]
-
Calculate NPV:
- NPV Formula: \[ \text{NPV} = \sum_{t=1}^{n} \frac{CF_t}{(1 + r)^t} - \text{Initial Investment} \] where \( CF_t \) is the cash flow for each year, \( r \) is the cost of capital, and \( n \) is the project duration (5 years).
- Cost of Capital (r) = 14% = 0.14
- Annual Cash Flow (CF) = $2,579,438.38 (from above)
- We will sum the present values of the cash flows for 5 years.
- Present Value of Cash Flows: \[ \text{PV} = CF \times \left( \frac{1 - (1 + r)^{-n}}{r} \right) \] \[ \text{PV} = 2,579,438.38 \times \left( \frac{1 - (1 + 0.14)^{-5}}{0.14} \right) \]
- First, calculate \( (1 + 0.14)^{-5} \): \[ (1 + 0.14)^{-5} \approx 0.5432 \]
- Now calculate the fraction: \[ \frac{1 - 0.5432}{0.14} \approx 3.246 \]
- Now, calculate the PV of cash flows: \[ \text{PV} = 2,579,438.38 \times 3.246 \approx 8,379,208.89 \]
-
Final NPV Calculation: \[ \text{NPV} = PV - \text{Initial Investment} \] \[ \text{NPV} = 8,379,208.89 - 10,608,505 \approx -2,229,296.11 \]
Thus, the NPV of the project at the current cost of capital is approximately -$2,229,296.11.