A city spends $15 million on a beach nourishment project that adds 1.8 million cubic yards of sand to 3 miles of beach. What is the cost per cubic yard of sand? (1 point)

Responses

$8.33 per cubic yard
$8.33 per cubic yard

$12.00 per cubic yard
$12.00 per cubic yard

$0.60 per cubic yard
$0.60 per cubic yard

$5.00 per cubic yard

1 answer

To find the cost per cubic yard of sand, you can use the following formula:

Cost per cubic yard=Total costTotal cubic yards of sand

Plugging in the values:

Cost per cubic yard=15,000,000 dollars1,800,000 cubic yards

Calculating that:

Cost per cubic yard=15,000,0001,800,000=8.33 dollars per cubic yard

So the cost per cubic yard of sand is $8.33 per cubic yard.