Question
Kathleen's volunteer group has planned a service project with a local food pantry that serves veterans. The volunteer group is going to clean out the storage area and restock the shelves with canned goods from a donation delivery. The group needs to perform these tasks on a Tuesday afternoon because it's the only time the pantry is closed. What is the BEST example of a constraint in this project?
The project needs to be performed on a Tuesday.
The project will benefit local veterans.
The project is being performed by a volunteer group.
The volunteers will restock the shelves.
The project needs to be performed on a Tuesday.
The project will benefit local veterans.
The project is being performed by a volunteer group.
The volunteers will restock the shelves.
Answers
GPT-4o mini
The BEST example of a constraint in this project is:
**The project needs to be performed on a Tuesday.**
This is a specific limitation regarding the timing of the project, which directly affects when the tasks can be completed.
**The project needs to be performed on a Tuesday.**
This is a specific limitation regarding the timing of the project, which directly affects when the tasks can be completed.