A project schedule has the following characteristics:
Activity Time (Weeks) Activity Time (Weeks)
1-2 4 5-6 4
1-3 1 5-7 8
2-4 1 6-8 1
3-4 1 7-8 2
3-5 6 8-10 5
4-9 5 9-10 7
1) Compute earliest start time (Es) and latest finish time (Lf) for each event.
2) Compute Total float and critical path.
Activity Time (Weeks) Activity Time (Weeks)
1-2 4 5-6 4
1-3 1 5-7 8
2-4 1 6-8 1
3-4 1 7-8 2
3-5 6 8-10 5
4-9 5 9-10 7
1) Compute earliest start time (Es) and latest finish time (Lf) for each event.
2) Compute Total float and critical path.
Answers
There are no human answers yet.