A person-hour represents the amount of work that one person can perform in one hour.
At a company, two different teams worked on identical projects. Team A consisted of 5 people working on the project for 2 hours a day for 8 weeks. Team B consisted of 4 people, who worked on the project for 3 hours a day for 6 weeks.
Determine the number of person-hours that was required for each team to complete the project, given that the company's work week is from Monday through Friday.
Explain what these values indicate about the relative efficiency of the two teams.
At a company, two different teams worked on identical projects. Team A consisted of 5 people working on the project for 2 hours a day for 8 weeks. Team B consisted of 4 people, who worked on the project for 3 hours a day for 6 weeks.
Determine the number of person-hours that was required for each team to complete the project, given that the company's work week is from Monday through Friday.
Explain what these values indicate about the relative efficiency of the two teams.
Answers
Answered by
oobleck
assuming 7-day work weeks,
A: 5(2*7*7) = ____
B: 4(3*7*6) = ____
A: 5(2*7*7) = ____
B: 4(3*7*6) = ____
There are no AI answers yet. The ability to request AI answers is coming soon!
Submit Your Answer
We prioritize human answers over AI answers.
If you are human, and you can answer this question, please submit your answer.