MNC company employed 25 men to do the official work in 32 days. After 16 days, it employed 5 more men and work was finished one day earlier. If it had not employed additional men, it would have been behind by how many days?
Just want to know
At the end how
Delayed time=18-16=2 days
How it happens
Just want to know
At the end how
Delayed time=18-16=2 days
How it happens