Asked by Anonymous

Worker A can complete the assigned work in 5 days. Worker B can complete it in 4 days. Worker C can complete it in 3 days. If all three workers are tasked to complete the same work together, how long will they take?

Please provide an adequate explanation of how to calculate the answer.

Answers

Answered by oobleck
1/x = 1/5 + 1/4 + 1/3
There are no AI answers yet. The ability to request AI answers is coming soon!