Question
In 2002, construction work began on a three-year contract at a price of $7,525,000. The firm uses the percentage-of-completion method of financial accounting purposes. The income to be recognized each year is based on the proportion of cost incurred to the total estimated costs for completing the contract. The financial statement presentations relating to this contract on December 31, 2002, are
Balance Sheet
Accounts Receivable $150,500
Construciton in progress $602,000
Less progress billings 562,000
Income Statement
Gross profit on construct. contracts $310,000
Determine the
a. Cash collected in 2002
b. Esitmated income on the construction contract
Balance Sheet
Accounts Receivable $150,500
Construciton in progress $602,000
Less progress billings 562,000
Income Statement
Gross profit on construct. contracts $310,000
Determine the
a. Cash collected in 2002
b. Esitmated income on the construction contract
Answers
Related Questions
Question 5: (50 points)
E 5-11 Income (loss) recognition; percentage-of-completion and completed...
E 5-11 Income (loss) recognition; percentage-of-completion and completed contract methods com...
A firm began the year making large profits. As time passed, the firm recorded the highest sales numb...
Assuming that 2001 is the base year, calculate the price index for 2002.
In 2002, the price index...