Gray Glaze requires 15 hours to put a new roof on a house. His apprentice, Anna Gandy, can record the house by herself in 20 ho...Asked by Carrie
Gary Glaze requires 25 hours to put a new roof on a house. His apprentice, Anna Gandy, can reroof the house by herself in 32 hours. After working alone on a roof for 20 hours, Gary leaves for another job. Anna takes over and completes the job. How long does it take Anna to complete the job?
Answers
Answered by
X
Gray's rate = 1/25
Anna' rate = 1/32
Job done by Gray = 20(1/25) = 4/5
leaving 1/5 of the job left to be done by Anna
time for Anna to complete
= (1/5) / (1/32)
= 6.4
It will take her 6.4 days to finish the roof.
Anna' rate = 1/32
Job done by Gray = 20(1/25) = 4/5
leaving 1/5 of the job left to be done by Anna
time for Anna to complete
= (1/5) / (1/32)
= 6.4
It will take her 6.4 days to finish the roof.
Answered by
henry2,
Gary completes 20/25 or 4/5 of the roof.
5/5-4/5 = 1/5 = 0.2 of roof remains.
1/32 = 0.2/T.
T = 6.4 Hours.
5/5-4/5 = 1/5 = 0.2 of roof remains.
1/32 = 0.2/T.
T = 6.4 Hours.
There are no AI answers yet. The ability to request AI answers is coming soon!
Submit Your Answer
We prioritize human answers over AI answers.
If you are human, and you can answer this question, please submit your answer.