Baldwin company make cabinets.one model,the Deluxe,has the followinh requirements.
Materials 40 feet of wood at birr 1.20 per foot
Direct labour 4 hours at birr 7 per hour
Variable overhead Birr5 per direct labour hour
During june 199x4, the company made 1,200 deluxe cabinates.operating results were as follows.
Materials purchased[58,000feet atbirr 1.15] birr 66,700
Materials used 51,200 feet
Direct labour[4,750 hours at birr 7.10] birr 33,725
Variable overhead birr 23,900
1,compute the standard variable cost per deluxe cabinate
2,compute the material price variancy.