A,B,C contract a work for 1020.together A and B are supposed to do 9/17 of work.how much C get?
ans 480rs

Answers

Answered by Scott
answer is correct
Answered by xyz
sir could you please explain this problem
Answered by PsyDAG
(1-9/17)1020 = 8/17 * 1020 = 480