Twelve man take 6 hours to finish a piece of work. After the 12 men have worked for 1 hour, the contractor decides to call in 8...Asked by shahzaman durrani
twelve men take 6 hours to finish a piece of work. after the 12 men have worked for 1 hour, the contractor decides to call in 8 more men so that the work can be completed earlier. how many more hours would 20 men take to compete the remaining work?
Answers
Answered by
Steve
the job is 12*6 = 72 man-hours of work.
In 1 hour, the 12 men have done 1/6 of the work, leaving 60 man-hours to do.
That will take 20 men 3 hours to finish up.