24 men works for 14 days, 2 days after they started working, 4 more men joined them and after 2 more days, 6 men left. How many more days will they now take to complete the remaining work?
8 years ago

Answers

Steve
So, the total man-days worked in the 14 days is

2*24 + 2*28 + 10*22 = 324

Without knowing how much total work is needed, there's no way to tell how many more days it will take.
8 years ago

Related Questions

tisha works 5 days a week as a paramedic. she has 10 holidays off and 3 weeks vacation every year. i... Sarita works 2 days each week. If her office is open 7 days each week, use pascal's triangle to find... A completes a works in 15 days and B completes the same work in 20 days. If they both work together... Linda works 3 days per week at $6 per hour. If she works 4 hours per day how many weeks will it take... Sam works 8 hours a day, 6 days a week, delivering flowers. And he earns $5.50 for delivering flower... 2 days 30 cents, 3 days 45 cents, 4 days 60 cents. The table shows the fine owed for an overdue lib... Kristina works out seven days a week. Lately, she has been tired, and her body aches. If she is over... Devon works 5 days each week. He delivers 840 cases of bottled water every day to his customers. He... Days- 2/ Fine- 30 cents/ Days- 3/ Fine- 45 cents/ Days- 4/ Fine- 60 cents. The table shows the fine... if jackson works every 3 days and tyson every 5 days how many days until they work together again
Ask a New Question
Archives Contact Us Privacy Policy Terms of Use