64 men can complete a work in 15 days.to complete the same work in 12 days how many more men are required
8 years ago

Answers

Answered by Steve
4/5 the time, so 5/4 the workers: 80

so, another 16 are needed.
8 years ago
There are no AI answers yet. The ability to request AI answers is coming soon!

Submit Your Answer


We prioritize human answers over AI answers.

If you are human, and you can answer this question, please submit your answer.

Related Questions

Does work work refer to the type of paid employment? Yes or no? Ok work... work = net force parallel to displacement lets say something was pushed up a ramp at... Subtract.show complete work (2x8 – x3 + 4x2 + 5) – (8x7 + 8x3 – 4x) Multiply. show complete work 2x + 4 by -5x2 – 3x – 2 WEEK 5 - Work Rates You work in retail. In the past you inventoried and shelved the weekly UPS shi... Work or no work? Work=ForcexDistance 1. A person holding a box of potatoes. No work 2. A batter... A, b, c can complete a work separately in 24, 36, and 48 days respectively. They started working to... look at the map to complete the following sentence. utahns are able to enjoy a cold winter skiing an... Complete each of the following sentences with either a compound subject or compound predicate. 1. Bl... c=7 b=6 a=? Complete the inequality so that it represents the whole-number values that side a cou...
Submit Your Answer

Question

64 men can complete a work in 15 days.to complete the same work in 12 days how many more men are required

Ask a New Question
Archives Contact Us Privacy Policy Terms of Use