If two people working together can do a job in 4 hours how long will it take the slower person to do the same job if one of them is 3 times as fast as the other?
8 years ago

Answers

Steve
If the quicker person takes x hours, then the slower person takes 3x hours.

1/x + 1/3x = 1/4
12+4=3x
x = 16/3
so, 3x = 16 hours for the slowpoke.
8 years ago

Related Questions

working together 2 people can mow a large lawn in 4 hours. One person can do the job alone one hour... 1. If x people working together make a total of y dollars after an hour of work. how much money will... If x people working together make a total of y dollars after an hour of work, how much money will z... Working together, two people can mow the lawn in 24 minutes. Working alone, one person takes 20 minu... Working together two people can cut a lawn of grass in 5 hours. One person can do the job alone in 1... Working together, two people can cut out a large lawn in 2 hr. One person can do the job alone in 1... What do people working in the same career cluster have in common? Two people working together to create a new machine is an example of what? O collaboration O inv... Two people working together to create a new machine is an example of what? O immigration O inventi... two people working together to create a new machine is an example of what? A. industrialization B....
Ask a New Question
Archives Contact Us Privacy Policy Terms of Use