                If it takes 10 men to build a house in 6 months how many men would be needed to build it in 4 months 
            
            
        Answers
                    Answered by
            Reiny
            
    10 men to build a 1 house in 6 months
10 men to build a 1/6 house in 1 months
10 men to build a 4/6 house in 4 months
1 man to build a 4/60 house in 4 months
60/4 men can build 1 house in 4 months
15 men can build 1 house in 4 months
or more simply
it takes 60 man-months to build the house
so it takes (60 man-months/4 months) men or 15 men to build the house
(the units of months would cancel)
    
10 men to build a 1/6 house in 1 months
10 men to build a 4/6 house in 4 months
1 man to build a 4/60 house in 4 months
60/4 men can build 1 house in 4 months
15 men can build 1 house in 4 months
or more simply
it takes 60 man-months to build the house
so it takes (60 man-months/4 months) men or 15 men to build the house
(the units of months would cancel)
                    Answered by
            Anonymous
            
    60
    
                                                    There are no AI answers yet. The ability to request AI answers is coming soon!
                                            
                Submit Your Answer
We prioritize human answers over AI answers.
If you are human, and you can answer this question, please submit your answer.