If 24 people can finish a job in 10 days how many more people need to be employed to finish the job in 4 days?
9 years ago

Answers

Answered by Anonymous
240 people/one day

so 240/4 = 60
so
60 - 24
9 years ago
There are no AI answers yet. The ability to request AI answers is coming soon!

Related Questions

Finish Color Matte Finish Glossy Finish TOTAL Red 8 9 17 Blue 2 4 6 Yellow 0 7 7 TOTAL 10 20 30 Find... I FINISH HOMEWORK, FINISH BRUSH TEETH, FINISH READ BOOK, GO BED. What would be the English equiva... so i'm trying to finish my lab and im trying to solve for the concentration, and the lab handout say... X -1 f (x) 0 1 2 Finish creating the input output table for the function f (x) = -(x + 1)^2 +... If 4 men can finish a job in 6 days,how long would it take 3 men to finish the job,working at the sa... x f(x) 0 1 2 Finish creating the input-output table for the function f(x)=20(3)^x X -1 f (x) 0 1 2 Finish creating the input output table for the function f (x) = -(x + 1)^2 +... Please finish y+7=6/7x-30/7 if y=3x+7 how do you finish the t-table for linear equation? X y -3... I finish it but don't know if it is right or wrong: Can someone tell me what I do wrong please....
Ask a New Question
Archives Contact Us Privacy Policy Terms of Use