if 6 workers complete a 1 km of roadway in 4 days. how long would it take for 4 workers to complete 3 km of roadway
Answers
Answered by
Reiny
6 workers do 1 km in 4 days
1 worker does 1 k m in 4/6 or 2/3 days
4 workers do 1 km in 8/3 days
4 workers do 3 km in 3(8/3) or 8 days
1 worker does 1 k m in 4/6 or 2/3 days
4 workers do 1 km in 8/3 days
4 workers do 3 km in 3(8/3) or 8 days
Answered by
Steve
6 workers do 1 km in 4 days
1 worker does 1 km in 4*6=24 days
1 worker does 3 km in 24*3=72 days
4 workers do 3 km in 72/4 = 18 days
or,
1km of road is 6*4 = 24 man-days
3km is thus 3*24 = 72 man-days
72 man-days/4man = 18 days
1 worker does 1 km in 4*6=24 days
1 worker does 3 km in 24*3=72 days
4 workers do 3 km in 72/4 = 18 days
or,
1km of road is 6*4 = 24 man-days
3km is thus 3*24 = 72 man-days
72 man-days/4man = 18 days
There are no AI answers yet. The ability to request AI answers is coming soon!
Submit Your Answer
We prioritize human answers over AI answers.
If you are human, and you can answer this question, please submit your answer.