The first group was responsible for making 160 suits while the second group was responsible for making 25% fewer suits in the same amount of time. The first team made 10 more suits each day than the second team and finished its job 2 days before the deadline date. How many suits did the second team make each day if it needed two days extra after the deadline to finish the assigned job?

Answers

Answered by Steve
group 1: 160 suits
group 2: 3/4 * 160 = 120 suits

If the 2nd team made x suits per day, then since it took 4 more days,

160/(x+10) + 4 = 120/x
x = 10

extra credit: how many days did the teams work?